How many days are allowed to file a major subdivision plat after signing?

Study for the New Jersey Professional Planner Exam with flashcards and multiple choice questions. Every question includes hints and explanations to boost your preparation. Get ready to pass!

Multiple Choice

How many days are allowed to file a major subdivision plat after signing?

Explanation:
In New Jersey, the timeframe for filing a major subdivision plat after it has been signed is set at 95 days. This period is important because it ensures that the approved plans are promptly filed with the local municipal authority, which helps maintain an orderly process in land development and ensures that all parties involved are aware of the approved subdivision layout. Filing within this timeframe is crucial for enforcing the terms of the subdivision approval. If developers fail to file within the 95-day period, they may need to go through the approval process again, which can lead to additional delays and costs. Understanding this timeline helps planners manage project schedules and deadlines effectively, ensuring compliance with state regulations regarding major subdivisions.

In New Jersey, the timeframe for filing a major subdivision plat after it has been signed is set at 95 days. This period is important because it ensures that the approved plans are promptly filed with the local municipal authority, which helps maintain an orderly process in land development and ensures that all parties involved are aware of the approved subdivision layout.

Filing within this timeframe is crucial for enforcing the terms of the subdivision approval. If developers fail to file within the 95-day period, they may need to go through the approval process again, which can lead to additional delays and costs.

Understanding this timeline helps planners manage project schedules and deadlines effectively, ensuring compliance with state regulations regarding major subdivisions.